IUIX_Progress::Pos Property

From PDF XChange PDF SDK
Jump to: navigation, search
Line 6: Line 6:
 
Gets/sets ''progress indicator'' at particular position to display task completeness.
 
Gets/sets ''progress indicator'' at particular position to display task completeness.
  
Indicator position will be calculated according to total [[PXV:IUIX_Progress_Size|progress size]] value.  
+
Indicator position will be calculated according to total [[PXV:IUIX_Progress_Size|progress size]] value, where '''Size''' value is considered as 100% of task completion.
  
 
For instance, if [[PXV:IUIX_Progress_Size|Size]] property is set to 200, and [[PXV:IUIX_Progress_Pos|Pos]] property is set to 150, progress indicator will display 75% task completeness.
 
For instance, if [[PXV:IUIX_Progress_Size|Size]] property is set to 200, and [[PXV:IUIX_Progress_Pos|Pos]] property is set to 150, progress indicator will display 75% task completeness.

Revision as of 09:01, 13 May 2015


Gets/sets progress indicator at particular position to display task completeness.

Indicator position will be calculated according to total progress size value, where Size value is considered as 100% of task completion.

For instance, if Size property is set to 200, and Pos property is set to 150, progress indicator will display 75% task completeness.

Syntax

HRESULT get_Pos([out, retval]  double*  pPos);
HRESULT put_Pos([in]  double  pPos);

See Also

See also IUIX_Progress, IUIX_Progress_Size.